PlatformRuvuma EnergyTanzania EntityMtwara LNG LtdMozambique EntityRuvuma Energy Industrial Park, LtdPlatform CAPEX$5.12 bnLNG Capacity4.11 MTPA · 3 TrainsLNG OEMBaker Hughes NMBL™Gas-to-Power450 MW GTCC · GE 9F-classNet Grid Export270 MW · TANESCO + EDMEco-Industrial Park810 ha · TZ + MZVP Network8 Hubs · 5 CountriesDirect Jobs10,000+ CreatedEPC LeadSamsung E&AFID SPV1 + SPV3Q4 2026FID SPV2Q1 2027First LNG Cargo2030Full Platform2032HoldCoMauritius-domiciledStructureDBFOMT PPP · BinationalConsortiumViability Gap · N-Gas · GEFCOPlatformRuvuma EnergyTanzania EntityMtwara LNG LtdMozambique EntityRuvuma Energy Industrial Park, LtdPlatform CAPEX$5.12 bnLNG Capacity4.11 MTPA · 3 TrainsLNG OEMBaker Hughes NMBL™Gas-to-Power450 MW GTCC · GE 9F-classNet Grid Export270 MW · TANESCO + EDMEco-Industrial Park810 ha · TZ + MZVP Network8 Hubs · 5 CountriesDirect Jobs10,000+ CreatedEPC LeadSamsung E&AFID SPV1 + SPV3Q4 2026FID SPV2Q1 2027First LNG Cargo2030Full Platform2032HoldCoMauritius-domiciledStructureDBFOMT PPP · BinationalConsortiumViability Gap · N-Gas · GEFCO
Large infrastructure construction project
Implementation Plan

From Pre-FID to Plateau

Ruvuma Energy's phased construction programme — from 2025 FEED completion through single financial close in 2026 to full platform operations at 4.1 MTPA and all 10 VP hubs by 2032.

2025
FEED & Pre-FID
2026
Financial Close
2030
First LNG Cargo
2032
Full Plateau

Five-Phase Implementation Programme

Phase 0In Progress

Pre-FID Preparation

Period
2024–2025
SPV
All SPVs
FEED commissioning — SPV1 EIP & power plant
FEED commissioning — SPV2 LNG liquefaction
AFC engagement letter and mandate preparation
ENH GSA (Gas Supply Agreement) advanced finalisation
Samsung E&A EPC basis of design agreement
Dual ESIA submission — NEMC Tanzania & MITADER Mozambique
Host government conditional approvals — Tanzania & Mozambique
KfW IPEX-Bank ECA mandate preparation (SPV2)
IFC revolving facility term sheet (SPV3)
Phase Outcome: Bankable model suite finalised · FEED complete · lender mandate letters · ESIA approved
Phase 1Planned

Financial Close & FID

Period
2026
SPV
SPV1 + SPV2
SPV1 Financial Close — AFC/AfDB/KfW @ 7.5% · 15yr · 3yr grace
ECA mandate finalised — KfW IPEX-Bank 20% cover SPV1
EPC contract signing — Samsung E&A (SPV2 liquefaction)
Baker Hughes NMBL/LM9000 supply agreement signed
SPV2 ECA mandate — KfW IPEX-Bank · Euler Hermes
SPV3 IFC revolving facility agreement signed
Land transfer and site mobilisation — Mahurunga Village
Marine jetty site works commence
Phase Outcome: All three SPVs at single financial close · EPC + OEM contracts active · site mobilised
Phase 2Planned

Construction — SPV1

Period
2027–2028
SPV
SPV1
EIP Phase 1 civil and structural works — 810 ha site
3 × 100 MW Baker Hughes NovaLT™ gas turbine installation
Industrial shed construction — 20 × 11,000 m² + 10 × 5,500 m²
Paved roads, truck terminals, multimodal cargo hub construction
Smart utilities — ZLD system, centralised cooling, rooftop solar
TANESCO/EDM grid connection — 220 MW net export works
SPV1 commissioning and first power generation
VP hub network construction — Tanzania hubs (3)
Phase Outcome: SPV1 first operations 2028 · 300 MW online · 220 MW grid export · EIP Phase 1 tenants
Phase 3Planned

Construction — SPV2 LNG

Period
2028–2030
SPV
SPV2
LNG liquefaction Trains 1 & 2 — Samsung E&A EPC construction
Gas pre-treatment facility (mercury, CO₂, moisture, NGL removal)
3 × 50,000 m³ full-containment cryogenic storage tanks
Marine export jetty — multi-berth LNG carrier + ISO tanker
ENH gas pipeline connection — Area 1 Mozambique
Ntorya gas pipeline connection — Tanzania field
High-pressure regasification unit — 50 bar domestic supply
SPV2 commissioning — Trains 1+2 at 1.5 MTPA · first cargo 2030
Phase Outcome: First LNG cargo 2030 · 1.5 MTPA Phase 1 · export to India and Kenya · SPV2 debt service
Phase 4Planned

Full Platform Operations

Period
2030–2032
SPV
All SPVs
LNG Train 3 construction and commissioning — full 4.1 MTPA
All 10 VP hubs operational — TZ, MZ, ZM, KE, DRC
Mozambique VP hubs (3) and Zambia hubs (2) online
Kenya hub (1) and DRC hub (1) operational
Full NGV conversion corridor network activated
EIP Phase 2 industrial tenants operational
Platform DSCR ~5.35× — full HoldCo consolidation
Platform plateau — full CAPEX deployment complete
Phase Outcome: 4.1 MTPA full capacity · 10 VP hubs active · Platform DSCR ~5.35× · Plateau 2032

Pre-FID Critical Milestones

The following milestones gate Financial Close. Any delay cascades into the construction programme and affects first cargo timing.

MilestoneTarget DateCriticalityGate Dependency
ENH GSA finalisation (Mozambique gas supply)Q2 2025HIGHPrerequisite for SPV2 FID
Dual ESIA approval (TZ + MZ)Q3 2025HIGHRequired for lender disbursement
AFC/AfDB mandate lettersQ4 2025HIGHTriggers lender due diligence
KfW IPEX-Bank ECA mandate (SPV2)Q1 2026HIGH20% ECA cover prerequisite
SPV1 Financial CloseQ2 2026HIGHSite mobilisation trigger
Samsung E&A EPC signingQ2 2026HIGHLong-lead equipment procurement
Baker Hughes equipment orderQ2 2026MEDIUM18-month lead time NovaLT™
SPV2 Financial CloseQ3 2026HIGHECA-heavy structure

EPC Work Package Breakdown

WPScopeSPVLead ContractorDuration
WP-01Site Preparation & Civil WorksSPV1Samsung E&A / Owner's Engineer18 months
WP-02Power Plant — Baker Hughes NovaLT™SPV1Baker Hughes OEM24 months
WP-03Industrial Shed ConstructionSPV1Local EPC Partner20 months
WP-04LNG Liquefaction — Trains 1 & 2SPV2Samsung E&A EPC36 months
WP-05Cryogenic Storage (3 × 50,000 m³)SPV2Samsung E&A30 months
WP-06Marine Export Jetty & RSRTSPV2Samsung E&A / Marine EPC28 months
WP-07Gas Pipeline Connection (ENH + Ntorya)SPV2Pipeline Contractor24 months
WP-08VP Hub Network (10 hubs)SPV3Regional EPC Partners30 months
WP-09LNG Train 3 (Phase 2)SPV2Samsung E&A EPC24 months
WP-10Grid Connection — TANESCO/EDMSPV1TANESCO / Owner's Engineer12 months

Owner's Engineer: An independent Owner's Engineer (OE) is appointed across all EPC packages — providing technical oversight, QA/QC, progress monitoring, and lender reporting throughout the construction programme. The OE mandate is required by AFC/AfDB financing conditions.

Engage as EPC or Technology Partner

Samsung E&A and Baker Hughes are engaged on the primary EPC and OEM packages. Sub-contractor and specialist supplier pre-qualification is open.